Project Schedule

The EA was completed in October 2013.  Changes to the Preferred Alternative, and related coordination with stakeholders such as RFTA and Garfield County regarding these changes, has been ongoing since early 2014.  FHWA will issue a decision document for the EA, which is planned to occur in spring 2018.   Upon completion of the National Environmental Policy Act process, subsequent project phases will follow, to include:

  • Preliminary and final engineering design  (Approx. 1 year)
  • Right-of-way acquisition (Approx. 1-2 years)
  • Project construction (2+ years depending on funding and project phasing).

  •